Test the construction schedule before you sign it.
The schedule you accept becomes the record every delay, claim and payment is measured against. Here is what to check in it, what to negotiate with the result, and a scorecard you can run on the file today.
A construction schedule review tests whether a schedule can be trusted before it becomes the baseline. It checks that every activity is tied to the work before and after it, that the critical path runs unbroken to the finish, and that the finish date comes from the logic and not from a date typed in by hand.
By Chimi Kadiya, founder of 1iQ · construction program and project manager for more than 15 years · updated November 2026
Six things to check before the schedule becomes the baseline.
None of these question how long the builder says the work will take. They ask whether the schedule will tell you the truth once work starts.
Every activity is tied in
Each activity should have work that comes before it and work that follows it. An activity with an open end can slip without moving anything else. Ask for the open ends to be closed before you sign.
The critical path reaches the finish
The longest chain of dependent work should run unbroken from the start to the completion date. If it stops short, the finish date is not being driven by the work. Ask to be walked through the critical path, activity by activity.
No dates are forced by hand
Hard constraints pin an activity to a date whatever happens before it. They make a schedule look on time when the logic says otherwise. Ask why each forced date is there, and have the ones that are not contractual removed.
The finish matches the logic
Recalculate the schedule and compare the finish with the one in the file. A gap means the date you were shown is not the date the plan produces. Negotiate from the date the logic gives.
Procurement and inspections are in
Long lead items and inspections decide when work can really start and close. A schedule without them is a best case. Ask for long lead items and inspections to appear as their own activities.
Float is believable
Float is the room an activity has before it delays the finish. Very high float usually means missing links. Negative float means the plan already misses its date. Agree up front who owns the float.
Score the schedule in about a minute.
Upload the file the contractor sent you. 1iQ recalculates it and runs the quality checks. You get a short scorecard to take into the conversation.
What to do with the result.
Agree the fixes
Share the problems and ask for a corrected schedule. It is a reasonable request while both sides still want the deal to close, and a builder with a sound plan will welcome it.
Record the baseline
Name the agreed schedule as the baseline in the contract, with its completion date. Every later change is then measured against one record both sides accepted.
Agree how progress is reported
Settle how often the schedule is updated and what counts as evidence of a delay. Disputes are shorter when the record was agreed before anything went wrong.
A reviewed schedule is only useful if someone keeps checking it against the site.
Inside 1iQ the agreed schedule becomes the baseline, and it stays fixed. Next to it sit two more dates: the working schedule, which moves only with approval, and the forecast, which is worked out from what has really happened on site.
When something slips, you see it the moment it happens, along with what it does to the finish and what it costs to carry. Nothing moves a planned date without a project manager approving it.
The full review also lists every finding with the activities involved, checks the plan against local weather and public holidays, and prepares a corrected copy you can send back.
Questions people ask.
What is a construction schedule review?
A construction schedule review tests whether a contractor's schedule can be trusted before it becomes the baseline. It checks that every activity is tied to the work before and after it, that the critical path runs unbroken to the finish, and that the finish date comes from the logic and not from a date typed in by hand.
Why should a developer or owner review the schedule before signing?
Once the contract is signed, the schedule becomes the record every delay, claim and payment is measured against. A schedule with gaps in its logic can hide a slip for weeks. Reviewing it first lets you agree the fixes while both sides still want the deal to close.
What is the DCMA 14 point schedule assessment?
It is a set of 14 quality checks first published by the United States Defense Contract Management Agency. It looks at things like missing logic, leads, lags, hard constraints, high float, negative float and overlong durations. It is widely used on large projects as a common yardstick for schedule quality.
Which schedule files can 1iQ read?
Primavera P6 files (.xer and .xml), Microsoft Project XML files, and Excel or CSV sheets.
Does 1iQ judge the contractor's durations?
No. The contractor owns the plan and its durations. 1iQ checks that the schedule can be tracked truthfully: the links, the order of work and the path to the finish. Durations, float and lags are shown but are not held against the schedule.
What does the free scorecard show, and what does the full review add?
The scorecard shows a score out of 100, how many quality checks passed, and the three biggest problems by name. The full review inside 1iQ lists every finding with the activities involved, adds site conditions such as weather and public holidays, prepares a corrected copy, and brings the agreed schedule in to be tracked against what really happens on site.
Is my schedule kept after it is scored?
No. The file is read to work out the score and is not saved. Your work email is kept so the 1iQ team can follow up.
See the full review on your own schedule.
Bring a schedule to a private briefing. We will run the full review with you and show how it is tracked once work starts.
Book a briefing